President of the Federal Court overturned the earlier decision that prevented the continuation of the works of construction of the dam.
Suspension of works in Teles Pires fell in 24 hours
Related Posts
Belo Monte Dam would be canceled if the law is interpreted in favor of human rights of communities
August 16, 2012
Again, the construction of the Belo Monte hydroelectric plant in the Brazilian Amazon was stopped because, according to the Federal Court of the First Region of the country, did not respect the Constitution and the ILO Convention 169
Globo: Justice determines suspension of works in Belo Monte hydroelectric
August 14, 2012
Brazilian Federal Regional Court determined the immediate suspension of the works in Belo Monte hydroelectric, in Para state, under penalty of a daily fine of nearly $ 250 000.
Teles Pires: Federal Justice annuls the environmental impact study
August 14, 2012
A federal court froze the work because it lacks the necessary congressional approval to be built on indigenous land.